{"id":14881,"date":"2023-09-06T10:27:31","date_gmt":"2023-09-06T15:27:31","guid":{"rendered":"https:\/\/www.imegcorp.com\/?p=14881"},"modified":"2023-12-14T11:46:59","modified_gmt":"2023-12-14T17:46:59","slug":"understanding-your-office-to-residential-conversions-structural-engineering-up-front-will-save-time-and-money-later","status":"publish","type":"post","link":"https:\/\/www.imegcorp.com\/insights\/blog\/understanding-your-office-to-residential-conversions-structural-engineering-up-front-will-save-time-and-money-later\/","title":{"rendered":"Understanding your office-to-residential conversion\u2019s structural engineering up-front will save time and money later"},"content":{"rendered":"

By Edwin Dean,\u00a0 Joe Gulden, and Doug Sweeney<\/span><\/p>\n

Office to residential conversion seems like a simple solution to a problem. Nationwide, <\/span>office vacancies stand at 17%<\/span><\/a>, with some big cities \u2014 San Francisco, Houston, Austin \u2014 topping 30%, while the U.S. faces a housing deficit of <\/span>3.8 million units<\/span><\/a>.<\/span>\u00a0<\/span><\/p>\n

But making an adaptive reuse project pencil out in a tight financing market isn\u2019t so simple. <\/span>Boston<\/span><\/a>, <\/span>New York<\/span><\/a>, and <\/span>San Francisco<\/span><\/a>, are considering ways to improve the financial incentives, change zoning policies and expedite plan reviews, but developers should get a full-service team assembled to take a hard look at a conversion before they get started.\u00a0<\/span>\u00a0<\/span><\/p>\n

This blog looks at structural engineering issues that could prove costly if they are overlooked in the initial stages, and the opportunities that exist to create appealing residential buildings.\u00a0<\/span>\u00a0<\/span><\/p>\n

Preliminary structural investigation<\/span><\/b>\u00a0<\/span><\/p>\n

To design a successful conversion project, an initial structural investigation is a key first step. Every building is unique, and older buildings may not have original structural drawings available or may have had substantial alterations. It\u2019s extremely important for a structural engineer to see the structural elements during a pre-acquisition consultation, or at the onset of the project, to help identify issues early in the development.\u00a0<\/span>\u00a0<\/span><\/p>\n

Getting to the structure is not always easy and may mean removing existing ceilings and wall finishes long before the general demolition begins. But skipping this key step can cause significant challenges \u2014 and added expense \u2014 later during construction.<\/span>\u00a0<\/span><\/p>\n

Adding natural light<\/span><\/b>\u00a0<\/span><\/p>\n

Housing facilities require exterior views in living units and it\u2019s important to consider how this can be accomplished in an office conversion. In a recent post-tension slab project, IMEG proposed two solutions to bring in natural light \u2014 a central atrium or exterior balcony cut-outs. The atrium was more straightforward structurally because it could avoid post-tension bands, but the owner preferred the exterior balconies.\u00a0<\/span>\u00a0<\/span><\/p>\n

To create the balconies, the post-tension bands on each slab edge would need to be eliminated, no small task. To add strength, IMEG offered two solutions \u2014 add beams below, or strategically locate new posts to reduce the slab spans. The owner preferred the second approach since the new posts could be integrated into the corners of the new windows. Fiber-reinforced polymer composites can also be used to provide external strengthening where additional strength is needed.\u00a0<\/span>\u00a0<\/span><\/p>\n

Structural design for mechanical, electrical, plumbing<\/span><\/b>\u00a0<\/span><\/p>\n

Coordinate with the structural engineering team as you plan unit layouts, plumbing, and HVAC. The architectural layout of a residential unit is unlikely to align with the office framing concept. If the units aren\u2019t aligned with the structure the job will be more complex.<\/span>\u00a0<\/span><\/p>\n

A conversion will greatly impact existing and new MEP systems, so the structural team will need to account for new floor and wall openings for conduit, piping, and HVAC. A ground floor restaurant or retail space can further complicate a conversion, as new shafts and penetrations will need to be run through the building. In older buildings, this can be a challenge, as the original shafts are likely smaller than current codes require, and the locations may be difficult to re-use.\u00a0<\/span>\u00a0<\/span><\/p>\n

Determining whether the floor plate is made of concrete, steel, or wood has a significant impact in the feasibility of a project. Steel or wood is generally easier to adapt in a conversion. If it\u2019s concrete, in particular post-tensioned concrete, you\u2019ll need to scan the slab to locate rebar and the tendons to avoid hitting them with new cores and openings.<\/span>\u00a0<\/span>\u00a0<\/span>\u00a0<\/span><\/p>\n

Conversions involving steel, heavy timber, and clay tile in historic structures pose additional challenges. A structural engineer can help account for those materials upfront, to avoid surprises and extra costs later.\u00a0<\/span>\u00a0<\/span><\/p>\n

Rooftop amenities<\/span><\/b>\u00a0<\/span><\/p>\n

There\u2019s good news on the roof. An office building\u2019s HVAC equipment is likely heavier (and perhaps outdated), and more than a new residential building would need. So, you should be able to reduce the amount of mechanical, electrical, and plumbing equipment on the roof. That leaves room (and reserve structural capacity) for desirable rooftop amenities, like a bar or pool, and the structural impact is not likely as much as you\u2019d think. A structural engineer can help evaluate the structure and creatively supplement the structural system where it is most needed. For example, pool walls can be used as structure and upturned beams can be hidden by a built-up raised decking system.<\/span>\u00a0<\/span><\/p>\n

Energy efficiency\u00a0<\/span><\/b>\u00a0<\/span><\/p>\n

To make the building attractive to the marketplace, it\u2019s important to update the exterior. Removing outdated and heavy exterior systems can improve aesthetics and energy efficiency.<\/span> When IMEG worked on the conversion of <\/span>100 Van Ness<\/span><\/a>, a 1970s-era office building in San Francisco<\/a>, the original precast-concrete wall system was replaced with new unitized glass curtain wall.\u00a0<\/span>\u00a0<\/span><\/p>\n

To make that switch, crews spent six months removing 1,600 precast-concrete panels, each weighing 7,000 to 14,000 pounds. Not only was the finished product a more modern glass building that appeals to tenants, but it also helped prevented a seismic retrofit because the curtain wall had much lighter loads than the original precast panels.\u00a0<\/span>\u00a0<\/span><\/p>\n

Occupancy<\/span><\/b>\u00a0<\/span><\/p>\n

Changing occupancy from office to residential triggers requirements for upgrading non-structural components of the building to comply with current code requirements. However, for the structural systems, where the existing building code is used, the trigger is based on a change in risk category instead of occupancy. Office and residential occupancies are in the same risk category, which would not trigger a wholesale upgrade of the structural system based on occupancy alone.\u00a0<\/span>\u00a0<\/span>\u00a0<\/span><\/p>\n

Several local jurisdictions have adopted their own triggers which do require structural system upgrades, so it is best to verify with the local jurisdiction\u2019s amendments. There also have been changes to how risk category is defined, so buildings with over 5,000 occupants or significant public assembly areas can now trigger a change in category. Substantial alterations to the structure or additions also would trigger upgrades. Historical buildings may also have their own code and unique requirements.<\/span>\u00a0<\/span><\/p>\n

Seismic<\/span><\/b>\u00a0<\/span><\/p>\n

Jurisdictions have significant variabilities in seismic requirements that can trigger upgrades for specific building changes in occupancy and use for office to residential conversions, and the associated alterations and additions. In most cases, newer construction buildings are \u201cbenchmarked\u201d and do not require a retrofit. Several jurisdictions have adopted local amendments affecting mandatory seismic upgrade triggers:\u00a0<\/span>\u00a0<\/span><\/p>\n

San Francisco<\/span><\/b>\u00a0<\/span><\/p>\n

Known as the \u201c2\/3 rule,\u201d San Francisco has adopted <\/span>SFBC 503.11.1<\/span><\/a>, which requires a seismic upgrade when two-thirds or more of the building floors are categorized as a substantial alteration \u2014 defined per floor as two-thirds or more of the floor area of a floor undertaking significant non-structural alterations. This is cumulative of any alterations within a two-year period. Retrofit is done to approximately 75% of new code levels.\u00a0<\/span>\u00a0<\/span><\/p>\n

Portland, OR<\/span><\/b>\u00a0<\/span><\/p>\n

The City of Portland, because of substantial increase in the seismic hazard in the region in the 1980s, enacted a city code, <\/span>Title 24.85 Seismic Design Requirements for Existing Buildings<\/span><\/a>, which triggers a seismic upgrade on a change of occupancy or use to more than one-third of the floor area and where the occupant load is more than 149. Retrofit is done to approximately 75% of new code levels, depending on the change in relative hazard classification.\u00a0<\/span>\u00a0<\/span><\/p>\n

Seattle<\/span><\/b>\u00a0<\/span><\/p>\n

In Seattle, <\/span>retrofits<\/span><\/a> are triggered when a significant investment extends the useful life of the building. Similar in intent to the San Francisco 2\/3 rule, this would likely trigger a retrofit on a significant conversion project. Retrofit is done to approximately 75% of new code levels.\u00a0<\/span>\u00a0<\/span><\/p>\n

Los Angeles<\/span><\/b>\u00a0<\/span><\/p>\n

Los Angeles Municipal Code 91.2.506.5.3<\/span><\/a> requires buildings be upgraded to 75% of new code level for change of occupancy from commercial to residential. Codes <\/span>91.8203<\/span><\/a> and <\/span>91.8204<\/span><\/a> require buildings meet current code.<\/span>\u00a0<\/span><\/p>\n

Every jurisdiction is different and conversions from office to residential may trigger a seismic rehabilitation, which will need to be determined on a building-by-building basis. Owners often ask for voluntary seismic strengthening with the goal of creating a safer structure or reducing the probable maximum loss (PML).<\/span>\u00a0<\/span><\/p>\n

Transforming vacant office spaces into vibrant residential units offers a promising solution to both high office vacancies and housing deficits. But this process involves intricate considerations to ensure success. While financial incentives, zoning adjustments, and expedited planning reviews are being explored in major cities, developers must assemble a comprehensive team to thoroughly assess conversion prospects in the tight financing landscape. Key structural factors include cost effectively introducing natural light, coordinating with mechanical, electrical, and plumbing integration, understanding the existing structure systems, addressing rooftop enhancements, understanding and accounting for seismic impacts, and navigating changes and amendments in national and local building codes.\u00a0<\/span>\u00a0<\/span><\/p>\n

By embracing these factors and engaging in meticulous planning, developers can unlock the potential of office-to-residential conversions, creating appealing and functional living spaces while simultaneously contributing to urban revitalization and addressing housing needs.\u00a0<\/span>\u00a0<\/span><\/p>\n